Concreters

How to Quote a Concrete Slab in Australia

A slab is never just the concrete — it's the dig, the base, the formwork, the steel and the finish. Here's how to quote a concrete slab so the site prep and ground conditions don't sink your margin.

The fastest way to lose money on a slab is to price the concrete and forget everything around it — the excavation, the base prep, the formwork, the reo and the finish. Every site is different, so a blanket rate per square metre misses the detail that actually costs. Here's how to quote a concrete slab so a shed pad and a house slab each get the number they deserve.

What a good slab quote covers

A slab quote is a stack of stages, not a single pour. Break it out before you price it:

  • Site prep and excavation — clearing, cut and fill, and getting machinery and trucks in.
  • Base and sub-base — compacted road base to the specified depth.
  • Formwork — timber or steel to define the shape and level.
  • Reinforcement — mesh or bar to the engineer's design, plus bar chairs.
  • Concrete — the mix and strength the job calls for, ordered per cubic metre.
  • Finish — broom, trowel, exposed aggregate or polished, each priced differently.
  • Spoil removal and curing — carting the dig away and protecting the pour, both real costs.

For any house or structurally critical slab, quote from the engineer's design, not a rule of thumb. AS 2870 covers residential slabs and footings, and the drawings dictate strength, mesh and footing depth — get them before you price.

Concrete and material costs in 2026

Concrete prices move with demand, fuel and cement costs, so get a fresh quote from your plant for every job. As a starting point for the core materials:

Concrete slab material costs in 2026
MaterialTypical costNotes
Concrete (25MPa)$200–$250/m³20MPa for shed pads, 32MPa for some house slabs
Reinforcing mesh (SL82/SL92)Priced per sheetTo the engineer's design
Formwork timberPriced per lin mPlus stakes, screws and release agent
Vapour barrier (200 micron)Priced per m²Under-slab plastic to stop moisture

Concrete strength follows the job — around 20MPa for shed slabs and 25MPa or 32MPa for house slabs, per the engineer. Add a vapour barrier and expansion joints to every slab, and order 5–10% extra concrete so a short load doesn't hold up the pour.

Labour and equipment

Pouring is the quick part — it's the prep, the finish and the clean-up that eat the hours. Price the full sequence: excavation, base prep, setting out, formwork, tying reo, the pour, screeding, trowelling and curing.

  • Skilled concreters charge around $80–$100/hour; labourers run $50–$65/hour.
  • A typical 60m² house slab takes roughly 60–80 hours of labour, depending on finish and access.
  • Price the plant too — excavators, skid steers, power floats, vibrators and laser levels all carry a cost.
  • A site the truck can't reach needs a concrete pump — often $1,500+ — and difficult access can add 15–25% to labour on its own.

Ground conditions, slab types and standards

Ground conditions decide the slab, and the slab decides the price. Check the soil before you commit to a design or a number.

  • Reactive clay soils, common across Australia, often need a waffle pod slab or bored piers — more material and more labour.
  • Conventional reinforced slabs suit stable ground; suspended slabs are for upper levels.
  • Get a soil report (geotechnical investigation) rather than guessing the foundation.
  • House and structural slabs need an engineer's design to AS 3600 and AS 2870; don't pour without it.

Common mistakes that eat your margin

  1. Guessing the ground. Reactive soil or rock changes the whole slab. Get a soil report or a proper inspection before you quote, not after you dig.
  2. Quoting off old prices. Concrete and steel move constantly. Confirm current rates with your plant (Boral, Hanson) the day you quote.
  3. Vague scope. Spell out who clears the site, removes the spoil and backfills. Leave it unsaid and it becomes your job for free.
  4. Forgetting difficult access. No truck access means a pump and slower labour. Confirm access and price the pump before you commit to a rate.
  5. No contingency. Build in at least 10% for rock, weather and the unexpected. Quote tight and the first bad day wipes your margin — aim for a 20–25% gross margin, not break-even.

Pro tips for a slab quote that holds

  • Order 5–10% extra concrete so a short load never stalls the pour.
  • Carry a minimum 10% contingency for ground and weather surprises.
  • Confirm current concrete and steel prices with your supplier for every quote.
  • Charge properly for difficult access — it drives both labour and equipment cost.
  • Read the soil report so you don't under-spec the foundation.
  • Itemise finishes and extras — exposed aggregate adds $30–$60/m² over a standard finish — so the customer sees the choice.

ServiceYak keeps your concrete, reo, formwork and finish rates in a reusable kit, so you can itemise a slab quote on site — mix, mesh and finish — and send a clean PDF the same day you inspect.

Frequently asked questions

How much does a concrete slab cost in Australia?

It depends on size, access and ground, but 25MPa concrete alone sits around $200–$250/m³, and a house slab carries far more in prep, steel and labour than the mix. A 60m² slab typically runs 60–80 hours of labour on top of materials.

How do I work out how much concrete a slab needs?

Multiply length × width × depth for the volume in cubic metres, breaking complex shapes into rectangles. Then add 5–10% for uneven subgrade and spillage — it's cheaper to have a little extra than to wait on a short load.

Do I need an engineer for a concrete slab?

For any house or structural slab, yes — the design must meet AS 3600 and AS 2870, and the drawings set the strength, mesh and footing depth. Quote from the engineer's plans, not a rule of thumb.